The Government of Assam on June 05, 2025, issued the Assam Solar Power Generation Promotion Policy 2025.
The following objectives are as stated:
• Develop a minimum of 3500 MW of Solar capacity by 2030.
• Ensure reliable, affordable, and clean energy supply.
• Attract private and public sector investment.
• To reduce the dependence on fossil fuels and further energy security in the State.
• Enable grid stability and renewable energy integration.
• Promote Assam as a regional energy hub.
Applicability and Duration
• Effective from the date of notification
• Valid till March 31, 2030.
• Applicable to all Grid Connected Ground mounted & floating solar power plants, rooftop solar power plants across Assam, including Battery Energy Storage Systems (BESS).
Scope of the Policy
• This policy will be applicable to all grid connected ground mounted solar power plants.
• floating solar power plants, rooftop solar power plant and standalone battery energy storage systems (BESS) established by power plant developers, in the State of Assam on the basis of "Assam Solar Power Generation Promotion Policy 2025" during the Operative Period
• All terms used in the Policy shall have the same meaning assigned in the Electricity Act-2003 and prevailing rules, regulations and guidelines notified by the concerned authorities etc.
[Notification No. PEL. 655345/1]