The National Stock Exchange (NSE) on November 14, 2025, notified regarding the Colocation initiatives.
The following has been stated namely: -
• The Exchange has announced that, effective November 17, 2025, colocation (Colo) participants may request removal of the side panel between two adjacent full racks to convert them into a High-Power Density (HPD) rack. This option is available only for racks located in Colocation Phase 13 and onwards.
• The conversion is allowed only when both racks are adjacent and share a common partition, and is subject to the Exchange’s infrastructure feasibility and availability.
• Interested participants shall submit requests as per Annexure A (enclosed below).
[Notification no. - NSE/MSD/71303]