The Ministry of Petroleum and Natural Gas (MoPNG) on November 10, 2026, issued a Policy for the Grant of Extension to Production Sharing Contracts (PSC) signed by the Government of India, awarding small, medium-sized, and discovered fields to private Joint Ventures.
The following has been stated:
• The Government has revised its March 28, 2016, policy for granting extensions to Production Sharing Contracts (PSCs) for 22 small and medium-sized discovered oil and gas fields, pursuant to the Oilfields (Regulation and Development) Amendment Act, 2025 and Petroleum and Natural Gas Rules, 2025. Contractors are required to submit an Operating Committee-approved extension application to the Ministry of Petroleum and Natural Gas (MoPNG), with a copy to the Directorate General of Hydrocarbons (DGH), after completion of half the contract term but at least two years before its expiry.
• DGH shall make its recommendation within six months, and the Government shall decide within three months of receiving the recommendation. During the extended period, the Government’s Profit Petroleum share will increase by 10% for the first 10 years, 5% for years 11–20, and 2.5% for years 21–30 over the share calculated under normal PSC provisions, while prevailing nomination-regime royalty and cess rates shall apply.
• Extension applications are subject to valid petroleum/mining leases, third-party reserves audits, submission of a Revised Field Development Plan (RFDP), proof of technical expertise, satisfactory past performance, achievement of at least 70% of approved development wells or committed production over the preceding 10 years, and compliance with Site Restoration Fund and Plan requirements.
• Contractors are also required to clear all statutory dues and provide a bank guarantee equal to 10% of the estimated annual expenditure under the approved work programme. Extensions may be granted until the end of the field’s economic life in one or more instalments of up to 30 years each. The Government may invite fresh bids or assign fields to ONGC or OIL where the prescribed conditions are not fulfilled, and reserves the right to reject an extension without assigning reasons.
[Notification No. - Expl-11019(18)/33/2026-ONG-IV]